COMPLETED PROJECTS and PROJECTS in PROGRESS
Contract Date of Date of
Project Name Client Job Description
Amount Contract Completion
Hydromechanical Equipment Manufacturing
BEYHAN 1 HEPP Kalehan Energy 13.553.136 $ 19/10/2011 30.02.2015
and Erection Works
Paravani Hydroelectric Plant Regulator, Valve Chamber, Plant Construction and Hydromechanical Equipment
House Construction And Hydromechanical Equipment Provision Georgia Urban Enerji Ltd. 19.332.984 $ 06/06/2012 12/08/2014 Manufacturing and Erection Works
Works
Hydromechanical Equipment Manufacturing
Artvin Dam and HEPP Alstom Renewable Energy Inc. 1.793.614 $ 14/03/2013 30/10/2015
and Erection Works
Sprial Case and Rings Fabrication.of
Paravani HEPP and Generator Upper&Lower
Heavy Welded Components of Arkun HEPP and Paravani HEPP Alstom Renewable Energy Inc. 483.819 $ 31/01/2013 12/08/2014
Brackets,Collector Cover, Upper Floor Cover
Manufacturings of Arkun HEPP.
Heavy Welded Components of Beyhan I HEPP / Turkey and Several Component Manufacturing ( Generator
İzmit Bay Bridge South Approach Viaduct Project Paravani HEPP Alstom Renewable Energy Inc. 455.030 $ 21/04/2013 27/03/2014 Upside&down connection parts)
Hydromechanical Equipment Manufacturing
Kiğı HEPP Özaltın İnşaat Ticaret ve Sanayi A.Ş. 8.146.754 $ 01/03/2013 In Progress
and Erection Works
Yukarı Kaleköy Dam and HEPP Voith Hydro Limited Sirketi 712.733 $ 03/01/2014 25/09/2014 Manufacturing of draft tube with cone
Hydromechanical Equipment Manufacturing
Yukarı Kaleköy Dam and HEPP Kalehan Energy 12.968.875 $ 19/12/2013 In Progress
and Erection Works
Artvin Dam and HEPP Alstom Renewable Energy Inc. 356.533 $ 18/02/2014 20/11/2015 Tailrace Bulkhead Manufacturing
Yukarı Kaleköy Dam and HEPP Voith Hydro Limited Sirketi 1.391.210 $ 18/02/2014 27/08/2015 Spiral Case Manufacturing
Yukarı Kaleköy Dam and HEPP Andritz Hydro 299.328 $ 16/05/2014 29/05/2015 Stator Frame Manufacturing
Artvin Dam and HEPP Project Alstom Renewable Energy Inc. 1.082.541 $ 01/10/2014 31/03/2015 Spillway Gate Manufacturing
Yukarı Kaleköy Dam and HEPP Voith Hydro Limited Sirketi 109.522 $ 11/09/2014 31/03/2015 Pit Liner Manufacturing
Yukarı Kaleköy Dam and HEPP Voith Hydro Limited Sirketi 100.153 $ 11/09/2014 20/02/2015 Spiral Case Pressure Test Head & Insert Ring
Inlet and Outlet Tunnel ( DT1 + DT2 )
Cetin HEPP Andritz Hydro 1.060.308 $ 22/09/2014 27/02/2015
Embedded Parts
Goktas I Dam and HEPP Bereket Enerji 134.426 $ 14/09/2015 22/12/2015 Lifting Equipment and Fish Elevator Crane and Car
Akıncı HEPP Bereket Enerji 336.029 $ 23/12/2015 In Progress 3 Unit spiral case manufacturing.
Manufacturing of Main Inlet Valve Upstream-
Gilboa Pumped Storage Power Plant GE-Alstom 147.653 $ 02/02/2016 In Progress Downstream Sleeves
Special Structures Electrical and Mechanical Works, Doha/Qatar Manufacturing of various pipes and fasteners
Hamitabat Natural Gas Combined Cycle Power Plant Enexio Hungary Zrt. 279.173 $ 24/03/2016 In Progress of Cooling Water Unit
COMPLETED PROJECTS and PROJECTS in PROGRESS SUB TOTAL 224.896.965 $
INDUSTRIAL PLANTS
Civil Works, Electrical Works, Machine
Contract Date of Date of Etibank Antalya Electrometallurgy Industries, Barite Grinding Plant General Directorate of Etibank 48,851,185 $ 09/01/1981 19/01/1982 and Equipment Supply and Installation,
Project Name Client Job Description Manufacturing and Erection Works (600 tons)
Amount Contract Completion
Steel Construction Manufacturing and
Erection (9830 tons); F16 Aircraft Factory
HYDROMECHANICAL EQUIPMENT MANUFACTURING AND CONTRACTS F16 Aircraft Factory, Production and Auxiliary Facilities TAI Tusaş Aerospace Industry Inc. 89,888,370 $ 12/04/1984 02/11/1987 Production Building Consisting of Three Parts
With 241.7 Meters Length and 40 Meters
Manufacturing of Tunnel Invert Form,
Kürtün Dam & HEPP Tunnel Formwork Nurol Construction Inc. 1.570.222 $ 29/09/1995 30/06/1996 Span, Eight Parts With 136.7 Meters and 30
Ø 12 m Inner Dia.(98 tons) Meters Span, and With a Truss Height of 10 m.
2x75+15 Tons Gantry Crane and Sivas Iron and Steel Factory, Steel Mill Comprehensive Steel Plant Continue Casting Unit Dust
Kürtün Dam Permanent Equipment Gantry Crane and Valves Nurol Construction Inc. 57.452.182 $ 10/02/1997 29/09/2003 Hyadromechanical Equipment, Penstock and Manufacturing Works Sivas Iron and Steel Factories Inc. 28,243,038 $ 12/02/1990 10/07/1991 Collection, Conveyor and Bunkers
Bottom Outlet Gate 8700 Tons Steel Construction, 1380 Tons
Draft Tube, Inlet Pipe and Accessories Sivas Iron and Steel Factory, Steel Mill Comprehensive
Fethiye Dam,Turbine Parts and Equipments K&AR Mühendislik ve Müşavirlik A.Ş. 783.995 $ 28/07/1998 30/10/1998 Sivas Iron and Steel Factories Inc. 75,665,140 $ 09/04/1988 31/08/1992 Mechanical Manufacturing, 19400 Ton
Manufacturing Works Manufacturing Works Equipment Erection
Concrete Formwork Car and Reinforcement
Kürtün Dam Concrete Formwork Car and Reinforcement Bar Car Nurol Construction Inc. 3.275.587 $ 01/03/1999 15/07/1999 General Directorate of State Stainless Steel Storage Tanks, Bottling Plant
Bar Car, Design, Manufacturing, Erection Nevşehir Rakı Factory 140,661,497 $ 15/12/1990 15/12/1991 and Technological Manufacturing Supply and
Çal HEPP, (2 x 1,1 MW), Turbine Parts and Hydromechanical Spiral Case, Draft Tube, Inlet Pipe and Monopolies Erection
Equipments Manufacturing K&AR Mühendislik ve Müşavirlik A.Ş. 127.638 $ 06/04/2000 15/09/2000 Accessories Manufacturing Works Technological Machinery Manufacturing and
Etibank-Elazığ Ferro-Chrome Plant General Directorate of Etibank 90,745,107 $ 25/09/1974 09/02/1977
Spiral Case, Draft Tube, Inlet Pipe and Erection 4300 Tons
Molu HEPP, Turbine Equipment Parts Manufacturing Kössler GmbH 255.275 $ 06/04/2000 15/01/2001
Accessories Manufacturing Works Turn-Key Crushing and Shifting Plant
Hydromechanical Equipment, Manufacturing Ovacık, Sand Preparation, Crushing and Sifting Plant Cam-İş Co. Inc. 9,057,068 $ 07/06/1995 19/12/1995 (50 Ton Steel Construction)
Gaziler HEPP, Permanent Equipment Manufacturing and Erection Gaziler Enerji ve Tic. A.Ş. 7.735.861 $ 14/09/1999 10/06/2002
and Erection (70 Ton Technological Equipment)
Hydromechanical Equipment Radial Gates, Ovacık Kuvarsit Mining Plant, Crushing Plant Cam-İş Co. Inc. 8,788,771 $ 13/06/1995 21/01/1996 Turn-Key Crushing and Shifting Plant
Kürtün Dam and HEPP Nurol Construction Inc. 32.593.811 $ 10/04/1997 09/08/2002
Valves Manufacturing and Erection Delivery Proportioning Silos and Dust
4 Each Radial Gates Manufacturing Works, Çayırova Fine Grinding Plant Cam-İş A.Ş. (Şişe-Cam) 19,769,398 $ 09/05/1996 21/12/1996 Collection Unit, Turn Key Plant, Design,
İnegöl - Yenişehir Boğazköy Dam TİSAN A.Ş. 1.274.511 $ 02/05/2005 30/11/2005
400 Tons Manufacturing Etc.
Hydromechanical Equipments Manufacturing Construction of Fine Grinding Building, Design,
Seyrantepe Dam and HEPP DARENHES Electric Production Inc. 3.461.657 $ 01/09/2005 01/10/2008 Çayırova Fine Grinding Plant Cam-İş A.Ş. (Şişe-Cam) 5,927,963 $ 17/07/1996 15/04/1997
and Assembly Works Manufacturing and Erection Works
Hydromechanical Equipments Manufacturing Stainless Tanks 4 Each,Carbon Steel Tanks 18
Çınarcık Dam YAYLA Timtaş 1.010.027 $ 21/06/2005 30/10/2008
and Assembly Works Erdemir - ET / TFS Facilities Project, Circulation Tanks & Steel Structure Marubeni Corporation 9,645,353 $ 28/02/1998 15/11/1998 Each Total 110 Tons, Steel Construction Total
150 Tons
Hydromechanical Equipment Manufacturing
Oşkan ve Berkman Enova Elektrik Üretim A.Ş. 10.840.776 $ 09/05/2008 30/12/2009
and Erection Works Enerjisa HRSG Project Gama A.Ş. 1,772,865 $ 12/05/1999 16/08/1999 HRSG Section & Modul Manufacturing Works
Hydromechanical Equipment Manufacturing Field Erected Fuel Oil Storage Tanks Capacity
Algeria Douera Dam Nurol Construction Inc. 3.410.437 $ 24/11/2007 27/05/2009
3
3
3
and Erection Works 5000 m , Double Shell 3000 m , 700 m , Shop
Fabricated Storage Tanks; Air Receiver Tank 6x50
Hydromechanical Equipment Manufacturing Çan Thermal Power Plant Alstom Power Teknotes Ltd. Şti. 3,359,740 $ 15/06/2001 25/06/2002
3
3
DIM Dam İçkale Construction Inc. 30.057.631 $ 04/06/1999 24/04/2009 m , Condansate Tank 7,8 m , Slop Oil Tank 7,6
and Erection Works
m , Hot water Accumulator Tank 1 m , Head Tank
3
3
Hydromechanical Equipment Manufacturing 2x6,3 m , Glycol + Water Tank
3
Yedisu Dam Hydromechanical Equipment Özaltın İnşaat Ticaret ve Sanayi A.Ş. 5.455.332 $ 09/03/2009 12/03/2012
and Erection Works Renovation of 6 Each Naphtha Tanks,
Hydromechanical Equipment Manufacturing Total Capacity 60.000 m³, Incl. Design Acc.
Yedigöl-Aksu Hydromechanical Equipments Borusan Enerji A.Ş. 1.749.810 $ 25/11/2009 05/01/2012
and Erection Works TÜPRAŞ IZMIT Renovation of 6 Each Naphtha Tanks Novation Tüpraş A.Ş. 21,614,264 $ 29/11/1999 18/07/2000 to API 650, Supply Aluminium Floating
Roof, Manufacturing, Erection, Civil Works,
Butterfly Valve and Gate Revision and
Beyköy Dam Zorlu Enerji 84.753 $ 18/05/2010 18/07/2010 Electrical Works and Fire Fighting Systems.
Erection
Total 9 Each, Cold Main Liming, Hot Main Liming,
Hydromechanical Equipment Manufacturing
Demirciler HEPP Hydromechanical Equipment Akfen Energy 1.013.639 $ 25/02/2011 12/12/2012 1 & 2 Carbonation, Reaction, Security, 1 st
st
nd
and Erection Works Kayseri Sugar Factory, Sugar Purification Tanks Kayseri Sugar Factory 698,792 $ 22/05/2003 30/09/2003
Stage Filter, 2 Stage Filter and Prelimer Vessels
nd
Fabrication, Transport and Erection Works.