Page 23 - Annual Report 2018
P. 23
Eyiste Viaduct, Konya/TURKEY
NUROL Park Project scope consists construction of nine multi - Under the scope of Ümraniye-Ataşehir-Göztepe Metro Line
2
purpose blocks with a total 323.500 m closed area on turn - key Project which was secured and signed with İstanbul Municipality
basis. Finally, a 50 floor tower and a base building complex with on 2017, construction of 13 km long double tube TBM tunnel, 2
a total of 142.000 m closed area were successfully completed train depots (NATM) and connection tunnels (NATM) is being
2
and handed over under our NUROL Life Project scope. implemented. Project includes total of 11 stations distributed as
5 main shaft+tunnel type, 4 cut and cover type an 2 tunnel type
The percentage of completion is more than 99% and water stations. Once completed, 2,47 billion TL worth project will
impoundment is expected to be realized on June 2019 in Ilısu
connect three district at Anatolian side of İstanbul.
Dam and HEPP Project, which is being constructed by an
international consortium under the leadership of NUROL as a Construction works at Yusufeli Dam Bridges project, that has
concrete faced rock fill dam with 24 million m dam body to been awarded to Nurol Construction in 2017 are ongoing in
3
generate 4,1 billion kWh energy per annum with 1.200 MW accordance with the schedule. 4 viaducts will be constructed
capacity. Total value of the project is expected to reach 780 with the balanced cantilever method. 644 m long Tekkale
million EUR upon completion. Ilısu Dam and HEPP will have (Hazuket) Viaduct, 695 m long Yusufeli Viaduct, 340 m long
the second largest dam body and fourth biggest installed Yusufeli Dam Viaduct and 530 m long Şilenkar viaduct constitutes
capacity of Turkey. the project scope. Contract value of the project is 355,8 million TL.
Provisional acceptance for the 325 million TL worth main Construction works are ongoing at for Silifke-Mut Motorway Project
contract works of the Construction Works of Hasankeyf Highway that has been awarded to Nurol Construction in 2017. Within the
Bridges project, which includes the construction of 465 m long scope of the 504,6 million TL contract, 14,2 km two by two
Hasankeyf-1, 1.001 m long Hasankeyf-2 and 169 m long Başur highway, 3 NATM tunnels with a total length of 6.860 m and a
bridges in Siirt and Batman provinces, was realized on October cable stayed 2. Kılıç Arslan Bridge will be constructed.
2017. 73,9 million TL supplementary works contract was signed
Value of completed items for our ongoing Ordu Ring Road
on April 2017 and construction works are ongoing in accordance
with the project schedule. Project has come to the original contract figure in year 2015 and
final contract value reached 550 million TL together with cost
Our MARMARAY Bosphorus Tube Crossing Project, which is escalations and another 20% additional contract granted by the
one of the major infrastructure projects of Turkey linking both Employer. 6 double tube tunnels with a total length of 9,5 km, 7
sides of Istanbul through an undersea immersed tube rail viaducts with a total length of 3 km, 3 bridges and 7 intersections
tunnel, was implemented by a Turkish - Japanese Joint Venture, constitutes the project scope of 2x2 lane 21,4 km long highway.
in which NUROL is among the local partners. Final acceptance As a result of the tender process arranged in order to get the
of the project, which had a value of approximately 1,3 billion project completed, extension works of the project were also
USD, was realized and operation was commenced as of 29 of secured by the Joint Venture led by Nurol Construction. 584,5
th
October 2013. million TL worth supplementary works contract was signed on
July 2017 and is ongoing in accordance with project schedule.
230 million TL contract was signed for Construction Works of
Eyiste Viaduct Project on December 2016. A 1.372 m long and Another contract for the landslide improvement works on
25m wide viaduct will be constructed under the scope of the the same route as in our Ordu Ring Road project was
project, which will become one of the highest balanced tendered and awarded to us in July 2016. The works in
cantilever beam viaducts of the world. The viaduct will have 2 scope was completed on October 2017 and provisional
end and 8 mid piers with heights ranging from 42 to 165 m. acceptance was realized. 10,7 km long section of Ordu
21