Eyiste Viaduct, Konya/TURKEY

             NUROL Park Project scope consists construction of nine multi -   Under the scope of Ümraniye-Ataşehir-Göztepe Metro Line
                                          2
             purpose blocks with a total 323.500 m  closed area on turn - key   Project which was secured and signed with İstanbul Municipality
             basis. Finally, a 50 floor tower and a base building complex with   on 2017, construction of 13 km long double tube TBM tunnel, 2
             a total of 142.000 m  closed area were successfully completed   train depots (NATM) and connection tunnels (NATM) is being
                             2
             and handed over under our NUROL Life Project scope.    implemented. Project includes total of 11 stations distributed as
                                                                    5 main shaft+tunnel type, 4 cut and cover type an 2 tunnel type
             The percentage of completion is more than 99% and water   stations. Once completed, 2,47 billion TL worth project will
             impoundment is expected to be realized on June 2019 in Ilısu
                                                                    connect three district at Anatolian side of İstanbul.
             Dam and HEPP Project, which is being constructed by an
             international consortium under the leadership of NUROL as a   Construction works at Yusufeli Dam Bridges project, that has
             concrete faced rock fill dam with 24 million m  dam body to   been awarded to Nurol Construction in 2017 are ongoing in
                                                   3
             generate 4,1 billion kWh energy per annum with 1.200 MW   accordance with the schedule. 4 viaducts will be constructed
             capacity. Total value of the project is expected to reach 780   with the balanced cantilever method. 644 m long Tekkale
             million EUR upon completion. Ilısu Dam and HEPP will have   (Hazuket) Viaduct,  695  m  long Yusufeli Viaduct,  340  m  long
             the  second  largest  dam  body  and  fourth  biggest  installed   Yusufeli Dam Viaduct and 530 m long Şilenkar viaduct constitutes
             capacity of Turkey.                                    the project scope. Contract value of the project is 355,8 million TL.

             Provisional  acceptance  for  the  325  million TL  worth  main   Construction works are ongoing at for Silifke-Mut Motorway Project
             contract works of the Construction Works of Hasankeyf Highway   that has been awarded to Nurol Construction in 2017. Within the
             Bridges project, which includes the construction of 465 m long   scope of the 504,6 million TL  contract, 14,2 km two by two
             Hasankeyf-1, 1.001 m long Hasankeyf-2 and 169 m long Başur   highway, 3 NATM tunnels with a total length of 6.860 m and a
             bridges in Siirt and Batman provinces, was realized on October   cable stayed 2. Kılıç Arslan Bridge will be constructed.
             2017. 73,9 million TL supplementary works contract was signed
                                                                    Value of completed items for our ongoing Ordu Ring Road
             on April 2017 and construction works are ongoing in accordance
             with the project schedule.                             Project has come to the original contract figure in year 2015 and
                                                                    final contract value reached 550 million TL together with cost
             Our  MARMARAY  Bosphorus Tube  Crossing Project,  which  is   escalations and another 20% additional contract granted by the
             one of the major infrastructure projects of Turkey linking both   Employer. 6 double tube tunnels with a total length of 9,5 km, 7
             sides of Istanbul through an undersea immersed tube rail   viaducts with a total length of 3 km, 3 bridges and 7 intersections
             tunnel, was implemented by a Turkish - Japanese Joint Venture,   constitutes the project scope of 2x2 lane 21,4 km long highway.
             in which NUROL is among the local partners. Final acceptance   As a result of the tender process arranged in order to get the
             of the project, which had a value of approximately 1,3 billion   project completed, extension works of the project were also
             USD, was realized and operation was commenced as of 29  of   secured by the Joint Venture led by Nurol Construction. 584,5
                                                           th
             October 2013.                                          million TL worth supplementary works contract was signed on
                                                                    July 2017 and is ongoing in accordance with project schedule.
             230 million TL contract was signed for Construction Works of
             Eyiste Viaduct Project on December 2016. A 1.372 m long and   Another contract for the landslide improvement works on
             25m wide viaduct will be constructed under the scope of the   the same route as in our Ordu Ring Road project was
             project, which will become one of the highest balanced   tendered and awarded to us in July 2016. The works in
             cantilever beam viaducts of the world. The viaduct will have 2   scope was completed on October 2017 and provisional
             end and 8 mid piers with heights ranging from 42 to 165 m.  acceptance was realized. 10,7 km long section of Ordu